Grand Ledge Public Schools Facilities Management Plan
Updated automatically every 5 minutes

Facilities Management Plan

Buildings, Technology Device and Infrastructure, Athletics Facilities, Heavy Equipment

2024-2027


Table of Contents

Introduction

Definition of Terms

Personnel

Strategic Plan

Buildings

Delta Center

Holbrook

Wacousta

Willow Ridge

Hayes

Beagle

Grand Ledge High School

Grand Ledge High School - Fine Arts

Grand Ledge High School - Auditorium

Delta Mills ECC

Neff ECC

Sawdon

Operations / Transportation

Technology Devices and Infrastructure

Athletic Facilities

Heavy Equipment


Introduction

Grand Ledge Public Schools is a large, mid-Michigan school district with approximately 5300 students and 700 staff members. Comprised of seven K-12 buildings, two early childhood centers, an operations center, and administration building, along with numerous athletic and activity fields, the district spans approximately 125 square miles in three counties. GLPS’s most recent upgrades have come from a 2018 bond proposal, which reshaped the district’s grade level bands, added facilities in multiple categories, and upgraded infrastructure. In addition, GLPS has a sinking fund, which is used for regular improvements.

This document serves as a record of needs, initiatives, and plans, and serves as a way to document priorities for upgrades and replacements, guided by the district’s strategic plan. It is important to note that this is a living document. As needs, costs, and realities change, the document will be updated. The revision date will always be included as a footer on each page, in order to ensure that stakeholders understand the ongoing nature of facilities management work. Not all boxes will always be filled in as needs, funding sources, and available information changes.

District leaders, including the superintendent; deputy superintendent; student safety supervisor; executive director for technology; athletic director; maintenance, grounds, and custodial supervisor; bond supervisor; and chief financial officer, met monthly throughout the 2023-2024 school year to create the initial draft, and it was shared with the board of education in July of 2024. The plan, moving forward, is for that team to meet on a regular basis to update the document. Community and stakeholder input is welcomed, and should be shared via regular communication methods with the leaders listed above.

Ultimately, the document serves as a record of needed upgrades and updates, and it will assist in budget planning moving forward.


Definition of Terms

Minimum Value - Facility or equipment upgrades that exceed $5000 are included in this plan. Any upgrades that fall below the threshold are viewed as regular maintenance items.

Costs - Costs will be updated annually for inflation, and are based on best estimates or quotes from vendors.

Budget Sources - Budget sources will be updated in the document as purchases approach, because of the nature of state budgets and voter approved revenue sources.

Priorities - Priorities for funding will be based on the district strategic plan, as well as answers to the following questions, in order:

  1. Does this cut/add violate a collective bargaining agreement, board policy, or other law or requirement?
  2. Does this cut/add directly impact students or student programming?
  3. Does this cut/add impact adults who directly impact students or student programming?
  4. Does this cut/add impact the ease with which adults do their work, but does not fall into the category of number 2 or number 3 above?

This means that there may be items on the list that get pushed to a later date, based on available funding.


Personnel

The following individuals represent the team that is responsible for the development and implementation of this plan:


Strategic Plan

Strategic Plan Goals

Buildings


Delta Center

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Boiler

Heating Building

2023

Replacement

$50,000-$60,000/per boiler X 2

2033/2035

Domestic Hot Boiler

Hot Water

2012

Replacement

$8,000-$10,000

2025/2030

General Fund Operations

Roofing

Old&Leaking

1987  100 hallway

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2025 to 2035

Roofing

Old&Leaking

1992 300 hallway

Replacement

Direct layover $10.65 sf ft Tear off $18.50

2030/2035

Roofing

Old&Leaking

2010 200 hallway

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2040/2045

Roofing

Old Past it’s life span

2020 roofing main office, main office hall, media center

Replacement

Direct layover $10.50 sq ft Tear off $18.50

2050/2055

A/C Compressor

Cooling building

2010

Replacement

$8,000-$12,000 X 2

2025/2030

General Fund Operations

Controls on the front end of the change aires

Regulates heating and cooling

2010

Replacement

$88,000

When funding is available?

Delta Center (con’t)

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

LED Upgrades/Indoor/outdoor

Energy efficient

1980’s

 Replacement

$385.00 per fixture

$585.00 per fixture with battery. 34 weeks lead time, includes installation

When funds are available?

Carpet replacement

Old, ripped

2000”s

Replacement

$4,100 per avg classroom

When funds are available?

Painting classroom and hallways

Needs a fresh layer of paint

2023 main hall/new wing

300 hall 2008

Rest of the building?

Re-Paint

$.80 cents a square foot

When funds are available?

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants

Holbrook

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Holbrook

Heating building

2020

Replacement

$50,000-$60,000/ per boiler X 2

2030/2035

Holbrook

Hot Water

2013

Replacement

$8,000-$10,000

2023/2027

General Fund Operations

Roof

Old past its life span

2015   Rm # 300 to 400 hallway area

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2035/2040

Roof

Old past its life span

2020 Rm# 100 and 200 hallway area

Replacement

Direct layover $!0.65 sq ft Tear off $18.50

2045/2050

A/C  Chiller Compressor

Cooling Building  

2020

Replacement

$10,000-$14,000 X 2

2030/2035

Carpet Replacement

Old, ripped

2019

replacement

$4,100.00 per avg classroom

2035/2040

Painting hallways/classrooms

Needs a fresh layer of paint

2019

Re-paint

$.80 cents per square foot

2035/2040

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants

Wacousta

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

2 Boilers

Heating the building

2024

Replacement

$50,000-$60,000/per boiler X 2

2034/2039

Roof

Roof replacement

2024

Replacement

2054/2059

Parking lot

potholes

2024

Replacement

$298,000

2049/2055

Domestic Hot water

Potable Hot water

2024

Replacement

$5,000-$8,000 per unit X 2

2034/2038

General Fund Operations

INDV cooling compressors per room

Cooling Classrooms

2024

Replacement

$3,000 per classrooms X 25

2034/2040

Carpeting

Classroom and Hallway

2024

Replacement

$4,100 per average room

2035/2040

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants


Willow Ridge

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

2 Boilers

Heating the building

2010

Replacement

$50,000 - $60,000/per boiler X 2

2025

Bond

Domestic hot boiler

Hot Water

2014

Replacement

$8,000-$10,000

2023/2027

General Fund Operations

Chiller

Cooling building

1997

Replacement

Bond $

2025

Bond

Controls

Upgrades

1997

Replacement

Bond $

2025

Bond

Cooling tower

Cooling building

1997

Replacement

Bond $

2025

Bond

Roofing

Old & Leaking

1997

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2030/2035

Parking lot repair

Potholes

1997

Replacement

Bond $

2025

Bond

LED lighting Indoor/Outdoor

Energy efficient

1997

Replacement

$385 per fixture $585 w/ battery. 34 week lead time. Price includes install

As funds are available.

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants

Hayes

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

3 Boilers

Heating the Building

2005 & 2006

Replacement

$65,000-$70,000/ per boiler x 4

2035/2040

Bond

 2 Hot water Heater

Domestic hot water

2014

Replacement

$8,000-$10,000 per unit X 2

2030/2035

General Fund Operations

Roof Cafeteria area

Replace roof partial

2025

Partial roof replacement

Tear off $18.50 sq ft

2030/2035

Bond

Controls

Neumatic’s

 1997

Full Replacement

2025

Bond

2 small AHU’s

Heating/Cooling office/cafe

1997

Full Replacement

2025

Bond

2 Large AHU’s

Heating/Coolingband/ choir,counseling

1997

Full Replacement

2025

Bond

Pumps/Motors

Heating

1997

Full Replacement

2025

Bond

Water softener

Softening the water

1997

Full

Replacement

2025/2030

LED Lighting

Energy efficient

1997,2020,2022

Partial replacement

$385 per fixture

$585 per fixture w/battery. 34 weeks lead time includes install

When funds are available

Bond

Hayes (con’t)

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Painting: hallway and classrooms

Fresh layer of paint

1997

Re-paint

$.80 cents per foot

When funds are available

Bond

Carpet

Class rooms has hard tile surface

1997

Replacement

$4,100.00

When funds are available

Bond

Bathroom upgrades

Old fixture and tile

1997

Full replacement

$30,000/50,000 per bathroom

When Funds are available

Roof Replacement

Old, time to replace

1993,1997,2010

Replacement

Direct layover $10.65 Tear off $18.50

2030/2035

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants


Beagle

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

3 Boilers

Heating the Building

2020

Replacement

$70,000-$80,000 per unit X3

2030/2035

1 Pool Boiler

Heating the Pool water

2021

Replacement

$40,000-$50,000

2030

Roofing Rm #200-215

Old & Leaking

2007

Replacement

Direct Layover $10.65 Tear off $18.50 sq ft

2037/2042

Roofing over Cafeteria & Kitchen

Old&Leaking

2007

Replacement

Direct Layover $10.65 sq ft

Tear off $18.50

2037/2042

Roof Aux Gym

Old&Leaking

2007

Replacement

Direct Layover $10.65 sq ft Tear off $18.50

2037/2042

Rest of the roof

New Addition

2020

Replacement

Direct Layover $10.65 sq ft Tear off $18.50

2055/2060

Chiller Compressors

Cooling

2010

2020

Replacement

Replacement

$12,000-$16,000 X 4

2025/2030

2030/2035

1 Domestic hot water Kitchen

Potable Hot water

2008

Replacement

$8,000-$10,000

2025/2030

General Fund Operations

3 Domestic hot water Building

Potable Hot Water

2020

Replacement

$8,000-$10,000per unit X3

2030/2035

General Fund Operations

1 Pool Chiller

Cooling the pool

2020

Replacement

$12,000-$16,000 X 2

2035

General Fund Operations

Beagle (con’t)

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants


Grand Ledge High School

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

3 steam boilers

Superior

Cleaver

Byran

Heating the building

1997

1984

2009

Replacement

$10,500,000.00 included in bond price

2025

Bond

1 pool boiler

Heating pool water

2021

Replacement

$30,000-$40,000

2031/2035

General Funds Operations

All classroom univents

Heating Classrooms

1997

Replacement

$10,500,000.00 included in bond price

2024/2025

Bond

Chiller

Cooling of High School

1997

Replacement

$10,500,000.00 included in bond price

2025

Bond

Cooling Tower

Cooling water before recooling

1997

replacement

$10,500,000.00 included in bond price

2025

Bond

2 Heating units in Auxiliary gym

Heating and Cooling

1958

Replacement

$10,500,000.00included in bond price

2024/2025

Bond

Controls

Replacing pneumatic  controls on the BMS

1997 and Older

Full Replacement

$10,500,000.00 included in bond price

2024/2025

Bond

Roofing

Ballast roofs

Early 80’s

Replacement

$975,000

2024

Bond

Pool resurfaced

Pool walls and floor

1997

Full  resurface

$170,000

2024-2026

Sinking fund

Grand Ledge High School (con’t)

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

LED Upgrades

Energy Efficient

1980’s

Replacement from Fine Arts to the North

$385 per fixture $585 per fixture w/ battery. 34 weeks lead time includes install

When funds are available

Roofing Aux gym, New gym, Aud,Math,pool area

Aged, old

1997

Replacement or layover

Direct layover $10.65 Tear off $18.50

2030/2035

Bathroom upgrades

Aged

1958-2010

Full Replacement

$30,000/50,000 per bathroom

2024/Present

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants


Grand Ledge High School - Fine Arts

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

2 Boiler

Heating the building

2023

Replacement

$50,000-$60,000 X 2

2033/2038

Roofing

2023

Replacement

Direct layover $10.65 Tear off $18.50 sq ft

2055/2060

Domestic Hot water Boiler

Potable Hot Water

2023

Replacement

$5,000-$8,000

2035/2038

General Funds Operations

Perforated vinyl window graphics

(19 windows)

Concealment of band room

N/A

New

$5,190 - $5,680

As funds are available, then replace every  7 to 10 years

School Safety Grants

3M Security Film

(19 windows)

Option for safety enhancement of band room

N/A

New

$8,710

As funds are available.

School Safety Grants

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants

Grand Ledge High School - Auditorium

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades


Delta Mills ECC

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

3 Boilers

Heating the building

Late 1970’s early 80’S

Replacement

$60,000

2024

Sinking Fund

Roof

Old & leaking

2016

Replacement

Tear off $18.50 sq ft

2036

2 Hot water heater

Potable hot water

2016

Replacement

$5,000  X 2

2025/2030

General Fund Operations

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants (or other means due to potential grant stipulations)

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants (or other means due to  potential grant stipulations)


Neff ECC

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Boilers

Heating building

2010

Replacement

$718,000

2024

Bond

Domestic Hot water boiler

Hot water

2013

Replacement

$5,000/$8,000

2024/2027

General Fund Operations

Roof Replacement

Old&Leaking

Early 80’s

Entire roof upgraded

$304,803

2024

Bond

A/C Compressors

Cooling

2010

Replacement

$8,000-$12,000 X 2

2025/2027

General Fund Operations

Controls

BMS

2010

Replacement

$60,250

2024

Bond

Water Softener

Soften water

2012

Replacement

$5,000/$8,000

2030

LED Upgrades

Energy Efficient

2021

Partial Replacement

$385 per fixture $585 per fixture w/ battery. 34 weeks lead time. Includes install

When funds are available

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants (or other means due to  potential grant stipulations)

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants (or other means due to  potential grant stipulations)

Sawdon

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

2 boiler replacements

Heating the building

1-2014 boiler

1-2018 boiler

Replacement

Replacement

$60,000 / $ 65,000 per boiler  X 2

2024/2026

2028/2030

First Floor cooling North End

Cooling Special services, Business office

2012

Replacement

$75,000

2024

Pending?

Second floor cooling North End

Cooling technology

2010

replacement

$75,000

2024

Pending?

Elevator

Bringing elevator up to code

Early 90’s

Refurbish

$100,000

2024

Sinking Fund

Roofing Gymnasium

Old &Leaks

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2030/2035

3rd floor roofing over classrooms

Old & Leaks

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2035/2040

Roofing ACR room

Old & Leaks

2010

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2045/2050

Hallways/roofing H.R & Academics

Old and Leaks

1997

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2035/2040

Sawdon (con’t)

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

LED upgrades

Energy Efficient

1980’s

Replacement

$385 per fixture

$585 per fixture w/battery. 34 weeks lead time. Includes install

When funds are available

Data Center UPS

Backup Power

2022?

Replacement

Data Center Climate Control

Data Security

2023?

Replacement

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants


Operations / Transportation

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

3 Existing WashBay Furnaces

Heating the wash bay

1997

Replacements

2025

Bond

3 Existing Door Heater for the Mechanics Bays

Heating the bays when doors are open

1997

Replacement

2025

Bond

Main Heating AHU

Heating the rest of mechanics shop

1997

Refurbish and/or full replacement

2025

Bond

Bus Loop Curbing

Old and deteriorating

1997

Replacement

2025

Bond

LED Lighting

Energy Efficient

2020

Partial Replacement

When funds are available

Salt Barn

Renting Space

None

New

$20,000

When funds are available

Radios / Antenna / Batteries (school radios)

Direct Communication for staff / admin.

Ongoing

(225 total radios so far within district)

Radios / Antenna / Batteries

$339 per SR24 radio

$22 per antenna

$49.95 per battery

 Varies - 3 to 5 yrs

Operations / School Safety Grants

Midland WR400

  (13 units)

Weather radios for buildings

Unknown

New / Replacements

Total cost = $975

As funds are available.

School Safety Grants

Operations / Transportation (cont.)

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants (or other means due to  potential grant stipulations)

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants (or other means due to  potential grant stipulations)

Technology Devices and Infrastructure

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Elementary Chromebooks

Student Chromebooks

March 2021

Replacement

370,000

Spring 2026

Intermediate & Middle Schools Chromebooks

Student Chromebooks

July 2021

Replacement

630,000

Spring 2026

Staff Chromebooks

Staff Chromebooks

July 2021

Replacement

60,000

Spring 2026

2025-2026 Total

1,060,000

Staff iPads

Staff iPads

2020-2021

Replacement

200,000

Spring 2027

Staff Computers

Staff Computers

2021-2022

Replacement

660,000

Spring 2027

Servers

Servers

2021-2022

Replacement

120,000

2026-2027

2026-2027 Total

980,000

Student Computers

Student Computers

2022-2023

Replacement

250,000

Spring 2028

Wireless

Network

2022-2023

Replacement

400,000

2027-2028

Switches

Network

2022-2023

Replacement

425,000

2027-2028

2027-2028 Total

1,075,000

High School Chromebooks

Student Chromebooks

2023-2024

Replacement

600,000

Spring 2029

Firewall

Network Security

2023-2024

Replacement

30,000

2028-2029

Camera Servers

Security

2023-2024

Replacement

90,000

2028-2029

2028-2029 Total

720,000

Student iPads

Student iPads

2024-2025

Replacement

650,000

2029-2030

General Fund

Apple TVs

Apple TVs

2024-2025

Replacement

60,000

2029-2030

General Fund

Copiers

Copiers

Replacement

500,000

2029-2030

UPSs

UPSs

Replacement

110,000

2029-2030

2029-2030 Total

1,320,000

Security Cameras

Security

Varies

Replacement

375,000

2030-2031

Projectors

Projectors

Varies

Replacement

625,000

2034-2035

Athletic Facilities

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

New Addition Branding

Directions, Community Pride, Program promotion

Never

New purchase

Spring/Summer 2024

Weight Room Record Board

Motivational/Spirit/Pride

Never

New purchase

Spring/Summer 2024

New Switch System for HS Main and Aux Gym Basketball Hoops

We need a better system to take stress off equipment

30 years

Replacement

2025

Replace and/or adjust West bleachers in HS Main Gym

Safety - fans must walk through the stands to enter bleachers

25 years

Replacement

As soon as funds are available

Install Fence to include the sidewalk on the North end of the stadium

Safety - Less congestion of fans getting to/from their seats

Never

New purchase

As soon as funds are available

Stadium Fencing Improvements

Curb Appeal for our district at a facility that is used constantly and visible to everyone

Mid 1990’s

New fencing

As soon as funds are available

Athletic Facilities (cont.)

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

LED Board at Stadium

Move scoreboard to visible area not facing sun - promote student broadcast work; promote district; promote events

New purchase

$170,000

2024-2025

Funds assigned within capital projects fund

Main Gym Sound System

Music and announcements at events

Current system is original to the gym. It has a cassette player

New system

As soon as funds are available

Siding Improvements - Beagle Dugout

Current siding it broken and worn down

Unknown

New siding

As soon as funds are available

Replace Tennis Barn with Pre-Fab Barn w/overhead door

Tennis barn is constantly broken into and it needs to be bigger and have easier access.

Over 15 years ago

New barn

As soon as funds are available

Softball Scoreboard

Difficult to read, constant bulb replacement, remote entry

20+ years

New scoreboard

$30,000

As soon as funds are available

Athletic Facilities (cont.)

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Fixing Serving Windows at Stadium Concessions

Stadium concessions

Original to the mid 90s stadium renovation

New frames and screens

As soon as funds are available

Back Stop Improvements at Gorman

Safety

New purchase

Net System - $3,200

Poles - $9,000

Concrete - $4,400

Boom Rental - $1,300

2024-2025

Upgrade to LED Lights at Stadium

Stadium is dark, more efficient, Safety and save money

Mid-90s stadium renovation

New lights

150K for lights

As soon as funds are available

New Scoreboards in High School Main Gym

Bulbs constantly need replaced; Parts nearly impossible to come by due to age; Accessibility issues due to hard wired controllers; Controllers difficult to get due to age

Original to gym construction in mid 90s

New scoreboard

15-17,000 EACH

As soon as funds are available

Athletic Facilities (cont.)

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Tennis Court Resurface/Fix

Safety - cracks continue to get bigger

This has been ongoing since it was built in 2010

Resurfacing and eventual full replacement

As soon as funds are available

Irrigation System at Gorman Baseball

Not working

Not known

New system

$20,000

As soon as funds are available

Gym Floor Replacement at HS Aux Gym

Old, slippery, doesn’t look good

Original

New floor

As soon as funds are available

New Floor Markings for PE Staff at Beagle Aux Gym

Needed for effective PE curriculum

Orignal

New markings

As soon as funds are available

Additional parking at track facility

Additional parking needed

Original

More spaces

Depends on spaces needed

As soon as funds are available

Sidewalk and Pad on East side of Track

Complete the facility

Original

Meet management

$60,000

As soon as funds are available

Community Pool Resurfacing

Needs upgrades to floor

2007

Replace enamel

$200,000

Summer 2025

Sinking Fund


Heavy Equipment

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Dump Truck

Daily use for grounds staff

Sold 2 years ago

New purchase

$83,000

2024-2025

Operations Budget

 ¾ ton work truck

Daily use for grounds

New purchase

$50,000

2024-2025

Operations Budget

1 ton work truck

Daily use for grounds

New purchase

$60,000

2024-2025

Operations Budget

New salter for Dump truck

Winter use

New purchase

$12,000

2024-2025

Operations Budget

Lawn mower

Daily use summer

New purchase

$15,000

2024/annually

Operations Budget

Bus Replacement

Annual need

Annual need

Annual need

$140,000/bus

Annually

Vehicle(s) Replacement

District use

Replacement

Food Service Truck

Food transportation

Replacement

Box Truck

District use

Replacement

Van(s)

District use

Replacement

Instrumental Music

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Last Updated: 3/19/25